Project Profile - Clarke Central High School Reroof |


|
Reroofing a school while it is in session always presents a number of
problems, but this one had several extra issues. Asbestos was present
in the old roofing system, and the tectum deck was bad in many places
and would need to be replaced as the roofing progressed.
In
order to help the owner with their budget for this school after the
bids were opened, we did a very thorough inspection of the building,
making cuts in the old roof in many places in order to determine the
extent of the deck replacement. We were able to reduce substantially
the dollar figure the owner needed to set aside for new decking,
thereby making the project more feasible. The asbestos abatement was
also handled by our firm and kept in a non-friable state, also saving
the owner the additional expense and potential liability of using a
separate abatement firm.
And to reduce the exposure to fumes and
noise while school was in session, our employees worked extended hours
during the summer recess the complete the major removal and replacement
completely. By working with the architect and roofing manufacturer, we
were able to substitute some products that would not require exposure
to asphalt fumes later in the project as well.
The project lasted over a year due to a large addition to the school, making our final contract close to $900,000. |
|